steercom:2007-02 [2007/02/07 19:39]
64.241.37.140 Second save during meeting. (CMB)
steercom:2007-02 [2007/03/08 16:39] (current)
206.197.251.1
Line 13: Line 13:
 ====== Date and Time ====== ====== Date and Time ======
   * February 7, 2007   * February 7, 2007
-  * 6:30 pm -+  * 6:30 pm - 8:00 pm
  
  
Line 40: Line 40:
 ||Book Sales|Total|60|| ||Book Sales|Total|60||
 ||S3|Sponsorship |250|| ||S3|Sponsorship |250||
-== Bank balance as of 1/​31/​07 ​     $ 1,074.75==+== Bank balance as of 12/​31/​07 ​     $ 1,074.75==
 == Pending Deposits 0 == == Pending Deposits 0 ==
 == Pending AP 0* == == Pending AP 0* ==
Line 56: Line 56:
 ||CC fees|| ​ <​$5.74>​|| ||CC fees|| ​ <​$5.74>​||
 ||Total|| ​ $73.21|| ||Total|| ​ $73.21||
- 
- 
- 
- 
  
 ====== Membership Report ====== ====== Membership Report ======
Line 71: Line 67:
     * 24 Jan SECURE ​ - 10     * 24 Jan SECURE ​ - 10
     * 25 Jan STCLUG ​ - 12     * 25 Jan STCLUG ​ - 12
- 
- 
- 
  
 ====== Mailing List Report ​ ====== ====== Mailing List Report ​ ======
Line 256: Line 249:
  
 ====== System Administration ====== ====== System Administration ======
 +  * Dark keeps crashing
 +    * Still having crashes due to hardware failures, averaging every other day now.
 +    * Need to quickly move to new systems or replace dark's hardware.
 +      * Gary predicts failure rate is increasing and will be more than once a day by end of month February.
 +      * System may be DEAD in/before APRIL!
 +      * This project needs **emergency priority!**
 +    * Gary will ask Allen @ Wash U if heat may be a problem!
 +      * Mike Knight does not belive that heat is the problem.  ​
 +    * Gary asked Mike Knight if he knows of any temp sensor.
 +      * Mike is not aware of any heat sensor.
   * Barry was supposed to talk to John Hodge about assisting with installing more AIX disk space.   * Barry was supposed to talk to John Hodge about assisting with installing more AIX disk space.
-  ​* Not yet able to talk to John Hodge, hopefully next week or so. +    ​* Not yet able to talk to John Hodge, hopefully next week or so.
-  * **Dark**__Underlined Text__ +
-    * Still having crashes due to hardware failures, averaging every other day now.  Need to quickly move to new systems or replace dark's hardware. ​  Gary predicts failure rate is increasing and will be more than once a day by end of month February. ​ **DEAD in/before APRIL!**//​__Italic Text____Underlined Text__// +
-This project needs **emergency priority!**//​__Italic Text____Underlined Text__// +
- +
- +
-                               The history: +
- +
-                                Feb = every other day (therefore project 15-20 this month) +
-                                Jan = 10 times +
-                                Dec = 6 times +
-                                April thru Oct = 13 failure in 7 months ​ (i.e. 2 times per month) +
-                                prior to April = 5 months between failures (i.e. Oct. '05) +
- +
-               Gary will ask Allen @ Wash U if heat may be a problem! ​  ​Considering University holidays for +
-lack of AC, change of seasons,​...this does look like a familair calender. ​  Gary will ask Mike +
-if he knows of any temp sensor. +
   * Michelob   * Michelob
     * Volume of mail stabilized once graymilter was activated.     * Volume of mail stabilized once graymilter was activated.
-    * Michelob depends on NFS filesystem from Dark!!!  **See above** emergency+    * Michelob depends on NFS filesystem from Dark!!! 
-  * Bud +  * BudBudlight ​- see Server Migration Project below.
-  * Budlight +
-  * WhatEverItIsNamed?​ +
-      ​+
  
 ====== Server Migration Project ====== ====== Server Migration Project ======
-  * Anything new? +  * Craig has been working on testing email. 
-  *+    * Craig to compare notes with Carl on Postfix configuration. 
 +  * Craig has been working on installing and configuring latest Drupal. 
 +  * Need to work on getting clients to configure to use IMAP. 
 +  * Jeff Muse got Mailman working and tested. 
 +    * Craig found a Drupal module for Mailman. 
 +    * Will be quick and simple to migrate mailing lists once we move the MX record.
  
 ====== Website Library ====== ====== Website Library ======
Line 291: Line 279:
   * No presentation uploads yet - waiting for migration   * No presentation uploads yet - waiting for migration
   * No migration means no progress this month.   * No migration means no progress this month.
-  * 
- 
- 
  
 ====== Other Old Business ====== ====== Other Old Business ======
-  * What else was done? +  * none
-  *+
  
 ====== New Business ====== ====== New Business ======
-  * Always more to do. +  * none
-  *+
  
 ====== Blue Sky ====== ====== Blue Sky ======
-  * What else do we want to consider? +  * none
-  *+
  
 ====== Follow-up and Action Items ====== ====== Follow-up and Action Items ======
-  * person ​task +  * Craig print out previous minutes. 
-  * +  * Craig - finish up work on email server. 
- +  * Craig - get people to test using IMAP to connect to Bud from their email clients. 
 +  * Craig - get with Chris Byrd to work on Drupal and other stuff. 
 +  * Carl and Craig - get together on Feb 13 or 14 during the day to work on new servers. 
 +  * Gary - follow up on Wash U phone lines. 
 +  * Gary - get more Lightning Talk people lined up. 
 +  * Stan - prepare for voting. 
 +  * Lee - provide power, food, and drink for workers.